June 27, 2025 Update
Street Closures7th St from CSAH 5 to 4th Ave and 3rd Ave NW remains closed. UpdateThe storm sewer construction on 3rd Ave continues on the south end. Roadway and subdrain construction along 3rd Ave is ongoing and progressing from north to the south following the storm sewer construction. 3rd Ave from 7th St. to 9th St. has been graded. Ongoing work in preparation prior to placing the aggregate section. Access will be limited to residents on 3rd Ave during street construction until it is reconstructed to aggregate.Underground utility construction on 7th St. is continuing with sanitary sewer main from 3rd Ave to CSAH 5. Watermain from CSAH 5 working west to 3rd Ave will follow.Temporary water service is active throughout the project. Underground staking and utility markings are ongoing. Please refrain from removing any of these from your lawn. Proposed subdrain service locations are currently marked with lath with purple ribbon. For relocation of the proposed subdrain, contact Ryan Fate (WHKS).Concurrently, MTC (MetroNet) and NPL (MERC) are performing operations in various sections of the project area to relocate lines for MetroNet and Minnesota Energy (MERC). For any questions or concerns regarding this work, please contact your service provider directly. Mail3rd Avenue Residents: Temporary mailboxes are located at the NW corner of 9th St and 3rd Ave. Mail is being delivered to this location. 7th Street Residents: Temporary mailboxes are located at the NW corner of 7th St. and 2nd Ave. Mail is being delivered to this location. SafetySlow down through construction zone. Driveway access will be limited during work hours, parking on side streets may be required.